Open
Gremista Landfill, Lerwick, Shetland - Phase 3 Construction
Shetland Islands Council
- Status
- Open
- Value
- Value not stated
- Closing
- Not stated
- Where
- Scotland
- Category
- Construction & building
- Published
- 14 August 2026 on Find a Tender
What the buyer says
The Gremista Landfill, Lerwick Phase 3 extension will primarily involve cut and fill earthworks, new haul roads, installing new surface water drainage ditches, pipework, manholes, and headwalls; placing a 500mm bentonite-enriched soil layer over the new landfill formation surface; followed by a 2mm HDPE welded geomembrane basal liner, protection geotextile, leachate collection pipework, and 500mm thick, clean aggregate drainage / protection layer. Capping works to the existing Phase 2 landfill area are also included and will comprise 1mm thick LLDPE welded geomembrane and restoration soils.